TUBEX Grout Injection Piles

Foundation is an experienced and trusted partner for TUBEX pile installations on a wide range of projects of varying complexities throughout California, Nevada, and Arizona.

What Are TUBEX Piles?

The TUBEX Pile (TP) and TUBEX Grout Injected pile (TGI) consists of a steel pipe casing attached to a patented displacement drill tip. The casing is both an integral part of the structural pile and a permanent lining for the placement of concrete after installation. The oversized displacement drill tip serves as an installation aid and provides the means through which grout is injected to produce a soil-cement mixture around the pile shaft in the case of the TGI.

Advantages

Of TUBEX & TUBEX Grout Injected Piles

The patented design of the pile tip can produce high-end bearing with or without grout injected through the tip.

Vibration Free: TUBEX piles do not generate vibration during installation and drastically reduce the risks associated with working close proximity to adjacent structures, new construction, or sensitive equipment.

Noise reduction: The installation equipment typically operates at around 65 db, which significantly reduces impact on surrounding entities (i.e. residential units, hospitals, businesses, etc.).

Soil Displacement: The proprietary tip is designed to cut and displace the material back into the surrounding soil.

Soil/Cement Mixture: The displaced soil along with the soil/cement mixture around the outside of the pile produces a high capacity pile when compared to traditional pipe installation. This process makes the effective diameter of the pile for calculation of friction capacity equal to the outer diameter of the displacement drill tip.

Full Length Steel Pipe Casing: The TGI pile consists of a full-length permanent casing. This full-length casing ensures that the pile maintains a uniform section even in loose sands, poor soils, and the site profile with a high water table. The full-length casing also permits inspection for the presence of water or deleterious material prior to the placement of concrete infill.

Increased Lateral and Tension Capacities: TGI piles are capable of withstanding high lateral and tension loading conditions because of the soil displacement and the permanent steel pipe casing. These casings are offered in all commercially available diameter and wall thickness to customize pile design to job needs coupled with rebar cages in the head of the pile.

Low Overhead/Limited Access: TGI Piles can be installed in existing structures with minimum overhead clearance as low as 10’ overall. The TGI equipment is capable of installing 26” deep foundations with an overall footprint of approximately 12’ wide x 28’ long x 9.5’ tall. Our specialized equipment provides an avenue for deep foundations.

TUBEX Grout Injected Pile Advantages:

  • No pile driving noise or vibration
  • Soil displacement (no drill spoils generated)
  • Composite pipe pile section with high capacity
  • Low overhead pile installation capabilities
  • Experience with DOT, OSHPD, and DSA
  • Unaffected by high water table, loose sands, or poor soils

Installation Methods

1

Step 1: A steel pipe is placed into the rotary head / drill table and clamped for rotation. The length of this section is dependent on site constraints and equipment selected for the project.

2

Step 2: The patented displacement drill tip and grout pipe is welded onto the bottom of the steel pipe casing, providing a watertight connection. The welded grout pipe is tested for water tightness.

3

Step 3: The drill table installs the pile in the ground by applying constant vertical load combined with rotary torque. If site access permits, piles will be installed in one piece to design depth. When overhead clearance is limited (i.e. seismic retrofits), the first section is installed to ground level. A second section of steel pipe casing is then spliced onto the previously installed piece. Depending on overall pile length, this process is repeated until the required depth is achieved. In the case of TGI, water is injected during installation as necessary.

4

Step 4: Upon reaching the required design depth in the case of TGI, grout is injected under pressure through the tip, mixed with the in-situ soil, and pushed around the outside of the pile to a predetermined height. The rotation of the TGI pile in conjunction with the patented displacement tip produces a soil-cement mixture around the pile.

5

Step 5: After the piles have been installed and the grouting process is completed, pile cap connection devices/reinforcing steel is placed as required per the approved design, and the pile is filled with concrete.

TUBEX Grout Injection Applications


  • Structural improvement of existing foundation structures during expansion and/or renovation.

  • Sites with restriction access, such as electrical substations.

  • Installation of piles in refineries or chemical plants where deep foundations are required in hazardous areas or projects are located above contaminated soils.

  • Retrofits within existing structures with low overhead clearances (hospitals, parking garages, high-rise buildings, etc.)

  • Projects where the control of water or hazardous materials are a problem, such as hazardous plumes or dump sites.

  • Projects with large tension, compression, and lateral loads.

  • Projects located above poor and/or liquefiable soil profiles or caving sands.

  • Projects with hydro-static water heads.