PG&E Ravenswood 0/1A
- Project Location: Palo Alto, CA
- Project Completion: 2010
- Solutions: 14” PCPS Piles (4 Qty.)
- Markets: Utility
- Techniques: Driven & Concrete forming
Foundation was awarded the contract to install 4 PCPS Piles at 55’ long to support utility poles. Foundation was also contracted to install cap connections, form and pour the footings.