Centinela Hospital
- Project Location: Inglewood, CA
- Project Completion: 2012
- Solutions: 20/26” Tubex Grout Injection (77 Qty.)
- Markets: Hospital
- Techniques: Drilled
Foundation was contracted to install (both indicator and production) 77 total Tubex Grout Injection Piles. At 60’ long, the piles required splicing. The project was a part of a large seismic retrofit program.