Located in Laguna Beach, California, Lift Station No. 2 was constructed in the middle 1950s and is in the need of a major repair and modernization. In this particular phase, Foundation was subcontracted to design and build a temporary beam and lagging shoring system.
The Project:
The project included, but is not limited to, the Construction of a new wet well dry well sewage list station. Included in this was the construction of new:
- VFD Operated Main Pumps
- Diesel Powered Emergency Pumps (valves, piping, instrumentation, and emergency generator)
- PLC-based Control System
- SCADA Communications
Foundation was subcontracted to carry out the design and construction of the shoring system by providing all necessary labor, materials and equipment. Partnered with Foundation, DH Charles designed a temporary soldier beam and lagging walls system that included two rows of internal bracings (whalers, corner struts and/or cross struts).
- A total of 41ea. 50 foot long, soldier piles were installed in order to retain/support 38 feet (max) of soil material
- More than 1000 lagging boards were installed accordingly.
The shoring system remained in place for approximately 7-8 months. Once the time elapsed, the contractor removed the system.
Challenges:
The site provided unique challenges given the conditions encountered at the two soldier pile locations differed. Because of this, it created risks that needed to be mitigated in tandem with the contractor, designers, and owners. Given that the rock material, at these two locations, had a compressive strength of over 14,000 psi, it required specialized equipment. In order to achieve this, our team relied on a suitable cluster drill to achieve soldier piles toe depths in these locations.
The Solution:
Foundation ensured that DH Charles’ design was constructible and suitable to Foundation’s means and methods. Furthermore, proper job coordination (both internally and with stakeholders) was incremental in completing the job on time. Foundation utilized “just in time” material delivery logistics (due to the job’s small footprint), and timely communication with the Contractor and District (especially during DSC). In all, this ensured a successful project and mitigated risks.