The San Rafael Harbor Bridge project follows the installation of Sheet piles and CISS piles for a new bridge being built in place of an existing/active roadway. The pile driving provided the abutment and pier support for the new structure.
Why Driven Piles Were The Solution:
The needs of the project owner were to meet an accelerated schedule, driven pile was the quickest solution. Since the piles were installed over San Rafael Harbor, steel casings were needed to protect against the tidal flow of the harbor. Piles were driven to refusal in sedimentary rock. As a result of this, thick steel casings were needed to take the high blow counts encountered during pile installation.
Challenges:
Construction was located on an active freeway offramp in San Rafael. Stage 1 of the project was to install all 28 of the abutment piles in a 55-hour continuous weekend closure of the offramp. All piles were installed and then covered up so the offramp could be reopened. Since there were these constraints, the weekend closure work required extensive planning/coordination efforts and required the use of 2 cranes in a tight work area. Our team encountered obstructions in multiple pile locations which was removed in order to continue pile installation. This presence of obstructions could not be accounted for and only added to the high-stress environment.
The project used the Accelerated Bridge Construction design which incorporates the use of precast concrete bridge elements. At the abutment locations, pile had to be within 3” of the design pile locations or else the precast element would not fit over the piles. At the Pier 2 location, the pile installation only had 1/2” of tolerance around the outside of the pile due to the size of the blockout in the precast element, as well as, the presence of continuous rebar running through the inside of the blockout. This meant that not only did the pile casings have to be perfect on location, but the installation of the rebar cages had to be installed perfectly so that the vertical rebars would miss the continuous rebars running through the blockouts.
The Solution:
Creative solutions included extensive templating for the Pier 2 locations. Foundation double and triple-checked the template prior to installing any piles. Piles were being installed to ensure the piles did not move off of location during install. All piles were vibrated into refusal to allow for better control of the pile during the initial installation before switching to the diesel impact hammer.
Pier 2 piles also required the installation of a temporary cofferdam due to the presence of water at the harbor. The temporary cofferdam provided a dry work environment for the crew, but it also worked as a sound curtain to meet the environmental restrictions associated with impact pile driving in water which could adversely affect the fish. The cofferdam was installed in the middle of the water, which provides access issues and requires its own set of templating to make sure the sheets are installed in the correct location.