The Michelson Water Recycling Plant in Irvine, California, underwent a significant upgrade by implementing a state-of-the-art Biosolids Energy & Recovery Facilities Project. This comprehensive system encompassed biosolids processing, biogas management, and energy recovery technologies. Upon completion, the Irvine Ranch Water District enhanced its sustainability practices by converting biosolids and biogases generated during the wastewater treatment process into valuable resources, promoting a more sustainable and environmentally responsible approach to wastewater management.

The Project:

Our team successfully executed the installation of 3,009 14-inch square driven piles across 14 distinct structures within a 4.6-acre footprint. This project involved the installation of over 26 miles of concrete piling, with top-of-pile elevations exhibiting a significant variation of up to 30 feet across the site.

To meet the project’s demanding schedule, Foundation employed a multi-rig approach, utilizing up to three rigs concurrently. At peak operations, up to 25 skilled crew members were actively engaged on-site.

Concrete pile installation was achieved using IHC SC-75 hydraulic hammers in conjunction with Manitowoc 3900 and Link-Belt 518 cranes. Each rig was equipped with a fixed lead system incorporating a drill and a 14-inch continuous flight auger.

In addition to the primary piling scope, Foundation installed approximately 240 temporary shoring beams and plates to support structures with finish floor elevations up to 20 feet below the existing grade. These elements were installed using a HPSI 250 vibratory hammer mounted on a Manitowoc 2900 crane.

The project also utilized a comprehensive fleet of supporting equipment, including two Pettibone Super 20 forklifts, one Komatsu mini excavator, one Bobcat skid steer, and multiple air compressors.


Challenges & Safety

  • Project Logistics & Coordination:
    • The 4.6-acre site presented significant logistical challenges, characterized by a compact footprint and the concurrent execution of multiple scopes of work alongside pile-driving operations.
    • Foundation Pile proactively coordinated pile installation schedules with project stakeholders to optimize workflow and ensure efficient site utilization for all trades involved.
  • Site Constraints & Material Management:
    • The site’s limited access point and restricted storage areas posed logistical constraints.
    • Foundation effectively managed the delivery of over 750 piles, ensuring the timely arrival of the correct pile lengths to align precisely with the established installation schedule.
  • Safety & Risk Management:
    • Given the project’s scope, the compact site, and the demanding schedule, maintaining a safe work environment for all personnel was paramount.
    • Foundation’s dedicated safety manager conducted regular site inspections to ensure adherence to all safety protocols. Daily safety briefings emphasized the importance of safety for all crew members.
    • To further incentivize safe work practices, the company implemented a safety rewards program, including safety appreciation lunches and raffles.
    • Foundation is proud to report that the driven piling scope of work was completed with zero safety incidents.

Cost-Saving Measures Employed

  • Optimized Pile Design for Cost-Effectiveness:

    • The project encompassed 14 unique structures, each with distinct load-bearing requirements.
    • To maximize cost-effectiveness, Foundation collaborated with Oldcastle Precast to tailor pile designs to the specific needs of each structure. This approach involved utilizing five distinct pile types in varying lengths, optimizing material usage, and minimizing overall project costs compared to a standardized approach.
  • Innovative Installation Techniques for Deep Foundations:

    • Over 180 piles required installation to depths exceeding 20 feet below the existing grade, necessitating their placement before subsequent excavation work.
    • To minimize material waste and associated costs, Foundation employed a 14-foot-long “follower” system for these installations. This innovative approach significantly reduced the need for excessively long piles, resulting in substantial material cost savings for the project.

Creative Solutions

  • Overcoming Groundwater Challenges in the Methane Digester Area:

    • High groundwater levels within the Methane Digester area presented significant logistical challenges for pile-driving equipment and material delivery vehicles.
    • To mitigate these challenges, Foundation Pile implemented a strategic solution by utilizing timber mats to create a stable and accessible work surface, ensuring efficient and safe equipment operation within the designated area. (See Exhibit 1)
  • Addressing Access Constraints for Subsequent Construction Phases:

    • The project schedule necessitated the completion of all pile-driving operations within the Methane Digester area before the commencement of subsequent construction activities.
    • To facilitate access for other construction equipment without compromising the integrity of the installed piles, Foundation implemented a carefully planned approach that ensured safe and unobstructed movement across the completed pile field.

Environmental Impact Mitigation

  • 1. Noise Mitigation Strategies:

    • The project site’s proximity to a wildlife sanctuary and nearby residential areas necessitated stringent noise mitigation measures.
    • To minimize noise impact, Foundation Pile employed IHC SC-75 hydraulic hammers equipped with noise-dampening coatings on all metal-to-metal contact points. This combination of specialized equipment and noise reduction techniques effectively mitigated noise levels to the satisfaction of the project owner.

    2. Environmental Stewardship and Wildlife Protection:

    • Project biologists expressed concerns regarding the potential impacts of construction equipment emissions on the avian population within the adjacent wildlife sanctuary.
    • To address these concerns, Foundation Pile strictly adhered to California Air Resource Board (CARB) regulations throughout the project, resulting in zero environmental violations. This proactive approach effectively mitigated any potential negative impacts on the local wildlife.