The American Center Phase II project located in San Jose, CA, included the addition of (2) six-story office buildings and a four-story parking garage. In this phase, Foundation installed 470 18" Precast, Prestressed Concrete Piles (PCPS) from 92' - 200' in length. Due to the demanding schedule, Foundation elected to utilize two pile drivers, a Manitowoc 400W and a Link-Belt LS338.

Challenges

  • Given the project was located next to a hotel and 2 existing office buildings, all deliveries had to be coordinated and executed so that the public and businesses adjacent were not interrupted.
  • Each pile location was predrilled through the landfill approximately 70ft and cleared of debris and leachate to install the 36″ casing.  As a result, this made pile location accuracy very difficult because the top 70ft of the pile had no skin friction with the soil.
  • Pile splices were required to be located a minimum of 35ft below the bottom of the landfill elevation to mitigate corrosion.  To mitigate this, Foundation submitted and approved the method of epoxy coating the splice before driving to provide a barrier from the surrounding landfill.

Innovative Construction Technique

  • To minimize splicing, Foundation cast full-length 18″ PCPS pile up to 145ft.  To limit damage, full-length piles that were fabricated 123ft or longer were lofted with a 4-point pick using two cranes.
  • Strict schedule coordination between CMP casing and pile driving to ensure safe working conditions and maximize pile driving efficiency.
  • Since the top of the piles, the CMP casing was unsupported and had no lateral movement, Foundation constructed and utilized templates at each predrilled hold to help each preserve the accurate location of the piles.
  • Foundation predrilled several days before mobilizing equipment.  As a result, this minimized crews working nearby of each other with the chance to encroach into another contractor’s safety fall zone.

Innovative Project Management

  • Due to the soil conditions, there were many obstructions encountered during predrilling.  To mitigate this, Foundation utilized a vibratory hammer with a mandrel and conical tip to clear out the CMP casing and clear the drilled hole to allow the pile to advance down to tip while driving.  This method avoided the necessity to excavate down to clear the obstruction, which would have delayed the schedule and increased costs.
  • To provide cost savings to the project, Foundation and Lusardi fabricated and installed only 2-3 piles in each pile cap at the beginning of production to allow Haley & Aldrich time to determine if the remaining piles could have revised shortened lengths.
  • Strict schedule coordination between CMP casing and pile driving to ensure safe working conditions and maximize pile driving efficiency.

Environmental Impact Mitigation

  • All cut-off material was salvaged and recycled for LEED credits.
  • CMP casing was permanently installed through the landfill layer before pile installation to mitigate the contaminated waste material from being pushed into the groundwater below.
  • The CMP casing was backfilled with gravel after pile installation, prevent down-drag on the pile during landfill settlement or liquefaction during seismic activity.
  • All personnel working on the project site were required to complete the HAZWOPER 40 training.
  • All personnel were required to be Asbestos and Methane trained.
  • Lastly, mobile drip pans were placed under equipment to ensure compliance with project SWWWP requirements.